Mumbaikars to face 20 day traffic diversion on Vashi bridge due to repair work

The diversion will begin from 1st Feb onwards and end on 20th Feb

From February 1st to February 21st, the Vashi creek bridge will face a major Traffic Diversion at Vashi bridge due to repair work.

Earlier the diversion was scheduled to begin on January 23rd but has been now postponed to February 1st. The repair work is for the expansion of the south-bound carriageway of the bridge.




The old creek bridge will be open only for all small vehicles going northward, out of Mumbai as it will be not able to handle heavy vehicles. The heavy vehicles will be diverted towards the Eastern Express Highway, from where they can turn right towards the Airoli toll plaza. The vehicles from there, the vehicles can take left from Diva circle at the end of the Airoli creek bridge and reach Patni road to connect to Thane-Belapur road. From there, the HMVs can travel towards Thane, JNPT, Pune.

“As the PWD authorities told us on Monday that they have postponed the work to February 1 till 21 due to administrative reasons, we have also postponed the traffic diversion,” said DCP (traffic) Nitin Pawar.  He even said that the diversion has been necessitated to prevent traffic snarls on the Sion-Panvel highway.

 

Tags
Show More

Surabhi Mahadevan

Words cannot describe my love for beauty, cats and water

Related Articles

Leave a Reply

Your email address will not be published. Required fields are marked *

Close