Photo: Pavan Kumar (cousin brother), Wikimedia Commons, CC BY-SA 4.0. A Vande Bharat Express train standing at Thane railway station. This is an illustrative photo of an Indian semi high speed train at Thane and not a bullet train or the planned bullet train station.
Quick answer: Thane is one of four planned Maharashtra stations on the Mumbai-Ahmedabad bullet train line, along with BKC, Virar and Boisar (NHSRCL stations page). Reports quoting officials place the Thane station in the Mhatardi area near Diva, which is a separate site from the existing Thane suburban railway station (Indian Express, 7 October 2025). The Ghansoli to Shilphata work is a tunnel of about 5 km, not a station, and Ghansoli is not on the list of 12 stations. A PIB backgrounder dated 3 July 2026 says the first service is expected in August 2027, on the Surat to Vapi section in Gujarat (PIB, 3 July 2026). The sources checked do not give a passenger opening date for Thane.
- Where the Thane bullet train station is
- Thane station construction status
- What the Ghansoli to Shilphata tunnel is
- Is a bullet train station planned at Ghansoli?
- Construction milestones are not opening dates
- Milestones timeline
- What this means for Navi Mumbai commuters
- Frequently Asked Questions
- How this guide was checked
- Sources
This is a researched guide and not an official notice. This site is not affiliated with NHSRCL, the Ministry of Railways or PIB. Construction progress and dates change, so confirm with NHSRCL.
Where the Thane bullet train station is
The Thane bullet train station is being developed in the Mhatardi area near Diva, in Thane district, according to officials quoted by The Indian Express (Indian Express, 7 October 2025). Some sources describe the nearby village as Dativali (Wikipedia). It is a separate site from the existing Thane suburban railway station. NHSRCL’s own station page gives no street address, so final passenger entrances, approach routes and interchange arrangements should be checked against later official announcements. This guide has not verified an entrance.
Do not assume an interchange with Thane railway station. The station is a separate development, and its passenger access connections need confirmation. In October 2025 the Indian Express reported that Deputy Chief Minister Eknath Shinde asked officials to explore links with Thane railway station, Kopar railway station and the Taloja Metro line. That was a direction to explore, not an operating or guaranteed connection.
NHSRCL’s Thane page says the station is close to the Ulhas river, and that this is why the entrance roof is shaped as an impression of waves (NHSRCL, Thane station). A few more facts come from NHSRCL’s project overview (NHSRCL project overview):
- Thane is one of the 12 stations on the 508 km line, and one of four in Maharashtra, the others being BKC (Mumbai), Virar and Boisar (NHSRCL stations page).
- A rolling stock depot is under construction at Thane, which is one of three depots on the corridor.
- The areas around the Thane and Virar stations have been shortlisted by the state authorities for Station Area Development schemes.
- NHSRCL says stations will be planned as transport hubs with metro, bus, taxi and auto links, without naming the links for Thane.
The Thane roads and metro changes around it are covered in our Thane metro and road projects guide.
Thane station construction status
A PIB reply to Parliament dated 22 July 2026 lists the Boisar, Virar and Thane stations together, with foundation works at an advanced stage and structural works taken up. The source table shows one status for the group, so it is not a separate Thane figure (PIB, 22 July 2026). An earlier PIB release dated 11 February 2026 said foundation work was in progress at Thane, Virar and Boisar. This guide was checked on 21 November 2026, but these updates are dated by their releases and do not show current work quantities.
What the Ghansoli to Shilphata tunnel is
NHSRCL describes a 21 km underground section between BKC and Shilphata, including India’s first 7 km undersea tunnel under Thane Creek. Of the 21 km, about 5 km is being cut with the New Austrian Tunnelling Method (NATM) and the remaining 16 km with tunnel boring machines (NHSRCL project overview). The pieces fit together like this:
| Component | Relationship |
|---|---|
| About 21 km | The whole BKC to Shilphata underground section |
| About 5 km | The Ghansoli (Sawli) to Shilphata NATM section |
| About 16 km | The tunnel boring machine section between BKC and Sawli |
| About 7 km | The undersea portion beneath Thane Creek, within the boring machine section |
The full 21 km is not under the sea. The Indian Express, reporting NHSRCL’s plan, describes the 16 km boring machine section as running between BKC and Sawli, near Ghansoli (Indian Express, 9 April 2026).
Official releases announced the Ghansoli to Shilphata excavation breakthrough on 20 September 2025 (PIB, 20 September 2025). NHSRCL describes the stretch as 4.881 km, commonly rounded to 4.8 km or about 5 km, which is the same NATM stretch at different precision. A breakthrough is an excavation milestone. Waterproofing, lining, finishing and equipment installation are separate stages, so it does not mean the tunnel was ready for passenger trains. Later updates put it at 4 km of 4.8 km in August 2025 (PIB, 6 August 2025) and 4.8 km completed in February 2026 (PIB, 11 February 2026). The Hindu reported on 3 April 2026 that NHSRCL officials described the tunnel as completed (The Hindu, 3 April 2026).
Is a bullet train station planned at Ghansoli?
No Ghansoli passenger stop appears in the published station list. A tunnel needs working sites, and Ghansoli is one of them. PIB says a 39 metre deep shaft was built at Sawli (Ghansoli) to launch a tunnel boring machine. The second machine started from there on 18 July 2026 and is driving towards Vikhroli, while the first started on 5 July from Vikhroli towards BKC (PIB, 18 July 2026). That is construction access, not a passenger stop.
NHSRCL lists the stations as Mumbai (BKC), Thane, Virar, Boisar, Vapi, Bilimora, Surat, Bharuch, Vadodara, Anand-Nadiad, Ahmedabad and Sabarmati (NHSRCL stations page). Ghansoli and Navi Mumbai are not on it. For the area itself, see our Ghansoli area guide.
Construction milestones are not opening dates
Finishing a tunnel, a foundation or a bridge is a construction milestone. A passenger opening date is a separate announcement about when trains start carrying passengers. The official pages say:
- The first high-speed rail service is expected to commence in August 2027, and the first section to open will be Surat to Vapi, both in Gujarat (PIB, 3 July 2026).
- In a Lok Sabha reply on 6 August 2025, the Railways Minister said the Gujarat portion between Vapi and Sabarmati is planned for completion by December 2027 and the whole BKC to Sabarmati section by December 2029, while adding that exact timelines can be fixed only after civil, track, electrical, signalling and trainset work is done (PIB, 6 August 2025).
- The Parliament reply on 22 July 2026 repeats that exact timelines for the entire project can be ascertained only after all associated works are complete (PIB, 22 July 2026).
The sources checked do not establish a confirmed passenger opening date for Thane. The Surat to Vapi first-service expectation and the earlier whole-project completion target should not be presented as Thane’s opening date.
Milestones timeline
| Date | What was stated | Source |
|---|---|---|
| 6 August 2025 | 4 km of the 4.8 km stretch between Ghansoli and Shilphata complete; work on the 21 km undersea tunnel section started | PIB |
| 20 September 2025 | Excavation breakthrough announced for the 4.881 km Ghansoli to Shilphata tunnel. Lining, finishing and equipment installation follow separately | PIB |
| 11 February 2026 | 4.8 km of tunnel between Ghansoli and Shilphata complete; foundation work in progress at Thane, Virar and Boisar; BKC excavation near completion | PIB |
| 2 April 2026 | NHSRCL officials describe the 5 km NATM tunnel between Ghansoli and Shilphata as complete, as reported by The Hindu | The Hindu |
| 9 April 2026 | Lowering and assembly of the TBM begins for the 16 km BKC to Sawli section; schedule reported as initial drive in July 2026 and main drive in October 2026 | Indian Express |
| 5 July 2026 | First TBM starts its 6 km drive from Vikhroli towards BKC | PIB, 18 July 2026 |
| 18 July 2026 | Second TBM starts from Sawli (Ghansoli) towards Vikhroli | PIB |
| 22 July 2026 | Boisar, Virar and Thane stations listed together: foundation works at an advanced stage, structural works taken up. BKC underground station: foundation works almost completed, base slab taken up | PIB |
| August 2027 | First service expected, Surat to Vapi section | PIB, 3 July 2026 |
What this means for Navi Mumbai commuters
- The project does not currently provide a passenger service for Navi Mumbai commuters. The Ghansoli work happens underground and at the Sawli shaft site, and no bullet train stop is planned at Ghansoli.
- Do not assume that the Thane bullet train station sits alongside Thane railway station. It is a separate site near Diva, and no official connection has been announced. For getting from Navi Mumbai to Thane today, see our Navi Mumbai local train guide.
- The Maharashtra stops a Navi Mumbai resident could plan around are BKC and Thane. Which will be more convenient depends on your starting node, the approach roads and the feeder services that are eventually announced, so watch NHSRCL for entrance and road access details.
- Expect construction traffic around work sites. For diversions and contacts, see our Navi Mumbai traffic guide. For metro links in Navi Mumbai, see the Navi Mumbai metro route map.
- This guide does not quote fares or timetables, because the official pages give none for the Maharashtra stations.
Frequently Asked Questions
Where is the Thane bullet train station?
Officials quoted by The Indian Express place it in the Mhatardi area near Diva, in Thane district, a separate site from the existing Thane suburban railway station. NHSRCL says it is close to the Ulhas river, and its entrance roof is shaped like waves. Final entrances and approach routes have not been confirmed here.
Will there be a bullet train station at Ghansoli?
No. NHSRCL’s list of 12 stations does not include Ghansoli. The Ghansoli (Sawli) site is a shaft used to launch a tunnel boring machine.
What has been completed in the Ghansoli to Shilphata tunnel?
The excavation breakthrough of the 4.881 km (about 5 km) stretch, cut with the New Austrian Tunnelling Method, was announced on 20 September 2025. It is part of the 21 km underground section. Lining, finishing and equipment installation are separate stages, so it does not mean the tunnel is ready for passenger trains.
When will the Thane bullet train station open?
The sources checked do not establish a passenger opening date for Thane. A PIB backgrounder dated 3 July 2026 says the first service is expected in August 2027 on the Surat to Vapi section, which is not Thane’s opening date.
Which Maharashtra stations are planned?
BKC (Mumbai), Thane, Virar and Boisar, according to NHSRCL.
Is the undersea tunnel finished?
No. The roughly 5 km NATM stretch had its excavation breakthrough in September 2025, but the 16 km section, which includes the 7 km undersea portion, is being built with tunnel boring machines, two of which have started their drives.
How this guide was checked
- The station details come from NHSRCL’s Thane station page, stations page and project overview, read on 21 November 2026.
- Tunnel and opening statements come from PIB releases dated 6 August 2025, 20 September 2025, 11 February 2026, 3 July 2026, 18 July 2026 and 22 July 2026. The Mhatardi location comes from an Indian Express report of 7 October 2025.
- The 5 km completion date and the TBM schedule come from The Hindu and The Indian Express reports of NHSRCL statements.
- Dates and distances are quoted as the sources state them, and no fare, timetable or opening date has been estimated.
Sources
| Point | Source |
|---|---|
| Station location (Mhatardi, near Diva) | Indian Express, 7 Oct 2025 |
| Excavation breakthrough | PIB, 20 Sep 2025 |
| Thane station description | NHSRCL, Thane station |
| Stations list and project overview | NHSRCL stations and NHSRCL project overview |
| Tunnel progress 2025 to 2026 | PIB, 6 Aug 2025 and PIB, 11 Feb 2026 |
| 5 km tunnel completion | The Hindu, 3 Apr 2026 |
| 16 km TBM plan | Indian Express, 9 Apr 2026 |
| TBM launches | PIB, 18 Jul 2026 |
| Opening expectation | PIB, 3 Jul 2026 and PIB, 22 Jul 2026 |
Checked 21 November 2026. Construction progress and dates change, so confirm with NHSRCL.