Quick answer: The Kharghar Turbhe link road (KTLR) is a CIDCO road project that is still under construction. It starts on the Sion-Panvel highway opposite Juinagar railway station and ends near Gurudwara Chowk and Central Park in Kharghar, with twin tunnels under the Parsik hills (CIDCO budget statement 2026-27). A Loksatta report of 20 November 2026 says both tunnels have been dug through, lining work inside them is under way, about 42% of the project was done at the end of October 2026, and the contract deadline is 31 December 2028 (Loksatta, 20 November 2026). The sources reviewed do not provide a confirmed public opening date. December 2028 is the completion deadline reported by Loksatta, not an announced date for traffic.
This is a researched guide and not an official notice. This site is not affiliated with CIDCO. Construction targets change, so confirm with CIDCO.
Current status
The latest cited update reports approximately 42% completion at the end of October 2026. Tunnel excavation is complete, while internal works, elevated sections and connecting roads remain under construction. The road is not open.
The route from near Juinagar to Central Park
CIDCO’s budget statement says the road starts from the Sion-Panvel Express Highway opposite Juinagar railway station and ends near the Gurudwara and Central Park in Kharghar. It describes an elevated corridor on the Turbhe side and an at-grade road on the Kharghar side, with the tunnel between them. Loksatta adds that the Juinagar end is next to Shirwane village and that the road passes under the Parsik hills.
The name refers to the corridor between Kharghar and Turbhe. The highway connection described in the sources is opposite Juinagar station, on the Turbhe and Shirwane side of the city, which is why a road called Kharghar Turbhe starts near Juinagar. In order, from the highway end:
- Connection to the Sion-Panvel highway opposite Juinagar station, next to Shirwane village.
- Elevated corridor on the Turbhe side.
- Twin tunnels under the Parsik hills.
- At-grade road on the Kharghar side, ending near Gurudwara Chowk and Central Park.
This outline follows CIDCO’s description. It is not a navigation map, and the sources reviewed do not describe intermediate exits, ramps or access points.
The Central Park Kharghar guide covers the park and the Kharghar area guide covers the node. The road is meant to link the Turbhe side of the city with Kharghar and, per Loksatta, to give the Taloja industrial area and Mumbra-Panvel highway traffic a shorter way to the Sion-Panvel highway towards Navi Mumbai.
Status by stretch
| Stretch | What the sources say is built | What is under construction | Source and date |
|---|---|---|---|
| Juinagar end: elevated corridor on the Turbhe side | Not described in detail | Viaduct pillars and the deck above them are being built, and CIDCO says the elevated work is progressing | Loksatta, 20 Nov 2026, citing CIDCO’s public relations department |
| Parsik hills twin tunnels | Both tunnels are dug through. Loksatta gives 29 June for the first and 31 August for the second | Concrete lining inside the tunnels. More than 800 metres of concrete inside was done by the end of October | Loksatta, 20 Nov 2026 |
| Kharghar side: road towards Gurudwara Chowk and Central Park | Not described stretch by stretch | CIDCO’s budget describes this side as at-grade. Loksatta says flyover, connecting roads and other works are still going on | CIDCO budget statement and Loksatta |
| Whole project | About 42% complete by the end of October 2026 | Remaining civil, systems and finishing work | Loksatta, 20 Nov 2026 |
What finished tunnel excavation means
Completing tunnel excavation creates the underground passage. It does not mean the carriageways, lining, operational systems, approaches and commissioning are complete. Hill International’s scope for the project includes ventilation, electrical and mechanical installations, and fire protection and life-safety systems (Hill International). Those systems are part of the project scope, and the sources reviewed do not report how far each has progressed.
Length, lanes, cost and who is building it
The sources give different figures. They may describe different scopes, design versions or ways of measuring, and the documents reviewed do not reconcile them, so each figure below is labelled with its source. Do not average them.
| Item | What each source says |
|---|---|
| Total length | CIDCO’s budget statement says 5.49 km (budget statement). Loksatta, citing CIDCO, says about 5.957 km (Loksatta). Hill International, the project management consultant, says nearly six km (Hill International) |
| Tunnels | Loksatta says two separate tunnels of about 1.76 km each, with one way traffic proposed in each. CIDCO’s budget says 1.763 km. Hill says a pair of bored tunnels of about two km plus a 700 metre cut and cover section. Hill also lists ventilation, electrical and mechanical systems and fire protection in its scope |
| Lanes | CIDCO’s budget describes a 4+4 configuration. Loksatta says four lanes in each tunnel. Hill describes six lanes outside the tunnels and four within them. The reviewed documents do not reconcile these descriptions, and Hill’s “four within the tunnels” is not read here as four per tunnel |
| Cost | Contractor-listed project value: ₹2,099 crore, in Loksatta and on the contractor’s page (Rithwik Projects). CIDCO budget estimate: about ₹2,195 crore. These are different kinds of figure and the sources do not reconcile them |
| Contractor | Rithwik and Everascon joint venture, per Loksatta, with TCE and Hill as project management consultant. Rithwik’s page gives an award date of 19 October 2023 |
| Budget provisions and revised estimates | The 2026-27 budget estimates show ₹345.79 crore as the revised estimate for 2025-26 and ₹600 crore as the budget estimate for 2026-27. These are provisions, not audited spending, and they do not show how much of the project is paid for or complete (CIDCO budget estimates, page 15) |
The December 2028 date: what it is and is not
The sources reviewed do not provide a confirmed public opening date. December 2028 is the completion deadline reported by Loksatta, rather than an announced date for traffic. Different pages display different targets, and none of them states which is the latest approved programme:
| Source | Target displayed |
|---|---|
| Rithwik Projects | 20 September 2028 |
| Loksatta, 20 November 2026, quoting project information | 31 December 2028 |
| Hill International | Completion by 2029 |
These are construction targets from different parties at different times. None is an opening announcement.
What to rely on and what not to rely on
- Rely on: the tunnels are dug through and the work now is lining, the elevated stretch and connecting roads, as CIDCO told Loksatta.
- Do not plan around: any opening date. A reported 2028 deadline is the latest contract date quoted, and it promises no specific day for traffic.
- Treat as an expectation: the cut in travel time from about 40 minutes to about 10 minutes. CIDCO and Hill both give this as what they expect once the road is open.
- Do not assume: toll, vehicle rules or which vehicles may use the tunnels. The reviewed sources do not establish an operational toll schedule or a permitted vehicle list. Check CIDCO’s notices and the budget page (CIDCO budget 2026-27 page).
What to use today
These routes come from our own area guides, which draw on Central Railway and CIDCO pages. Check live timings before you travel.
| Journey | Existing option | Where to read more |
|---|---|---|
| Kharghar to Turbhe | Central Railway’s Trans-Harbour line serves both Kharghar and Turbhe. A journey needs a service that calls at both stations, so check that your Thane to Panvel train shows a time at both | Kharghar railway station guide and Turbhe area guide |
| Kharghar to Juinagar, Nerul and Vashi | The Harbour line runs through Kharghar, Belapur CBD, Nerul and Juinagar towards Vashi. Turbhe is not on the Harbour line | Kharghar railway station guide |
| Kharghar to Juinagar, Turbhe or Vashi by road | Existing roads, including the Sion-Panvel highway, until the new corridor opens. Check tolls on your route | Kharghar area guide and toll plazas guide |
| Kharghar to Belapur by Metro | Navi Mumbai Metro Line 1 runs between Belapur and Pendhar and has a Central Park station. It is an option within its own corridor, not a replacement for a Kharghar to Turbhe connection | Navi Mumbai Metro guide and Central Park Kharghar guide |
For where to live around Kharghar and Panvel, see Panvel vs Kharghar vs Taloja. For a separate, much larger CIDCO road, see our Thane to airport elevated road guide.
Which areas it affects
Kharghar is under Panvel Municipal Corporation (PMC) and Turbhe is under Navi Mumbai Municipal Corporation (NMMC), according to our area guides. The road itself is a CIDCO project, so CIDCO is the body to ask about it, and neither corporation is named as the builder in the pages linked here. CIDCO and Loksatta name Kharghar, Juinagar and Turbhe, and Loksatta adds the Taloja industrial area, as the places it connects. The sources do not describe a direct link to Kamothe or Panvel town, so do not assume one.
Frequently Asked Questions
Where does the Kharghar Turbhe link road start and end?
CIDCO’s budget statement says it starts on the Sion-Panvel Express Highway opposite Juinagar railway station and ends near the Gurudwara and Central Park in Kharghar.
Is the Kharghar Turbhe link road open?
No. It is under construction. Loksatta reported on 20 November 2026 that both tunnels are dug through and lining and elevated work continue. About 42% was complete at the end of October 2026.
When will the Kharghar Turbhe link road open?
The sources reviewed do not provide a confirmed public opening date. Loksatta reported a contract deadline of 31 December 2028, the contractor lists 20 September 2028 and Hill lists 2029. These are completion targets, not announced dates for traffic.
How much will it cost?
The contractor-listed project value is ₹2,099 crore, and CIDCO’s budget gives an estimated cost of about ₹2,195 crore. These are different kinds of figure, and the sources reviewed do not reconcile them.
Will the trip really take 10 minutes?
CIDCO and Hill expect it to fall from about 40 minutes to about 10 once the road opens. That is an expectation, not a guarantee.
Is there a toll?
The reviewed sources do not establish an operational toll schedule or a permitted vehicle list. Check CIDCO’s notices.
How this guide was checked
- Route, length, lanes and estimated cost come from CIDCO’s 2026-27 budget statement and budget estimates, read on 22 November 2026.
- Progress, tunnel dates, the 42% figure and the 31 December 2028 contract deadline come from a Loksatta report of 20 November 2026 that quotes CIDCO’s public relations department. The report is in Marathi and is paraphrased here.
Sources
| Point | Source |
|---|---|
| Route, length, lanes, cost estimate | CIDCO budget statement 2026-27 and CIDCO budget page |
| Budget figures | CIDCO budget estimates 2026-27, page 15 |
| Progress, tunnel dates, 31 December 2028 deadline | Loksatta, 20 November 2026 |
| Consultant, scope, 2029 target | Hill International project page |
| Contractor, award date, September 2028 date | Rithwik Projects project page |
| CIDCO site review, route description | Construction World, 6 May 2025, citing PTI |
Checked 22 November 2026. Targets and figures change, so confirm with CIDCO.