Entrance of Karjat railway station in Maharashtra

Panvel-Karjat Suburban Railway Line: Route, Stations and Opening Status

Transport & Commute

Photo: Superfast1111, Wikimedia Commons, CC BY-SA 4.0. Karjat railway station entrance. This is an illustrative photo and does not show the new line.

Latest status, checked 15 November 2026: The new Panvel to Karjat suburban corridor is not open to passengers, and no start date for local trains has been announced. This guide covers that new corridor. An existing railway already connects Panvel and Karjat and carries other train traffic, so the opening status here concerns only the new local train service. MRVC was reported on 7 November 2026 as targeting completion of the work by the end of December 2026, after which the project is to be handed over to Central Railway (Sakal report). Completion of work is not the same as a service start.

This is a researched guide and not a railway notice. This site is not affiliated with MRVC or Central Railway. Dates are targets and can change, so check Central Railway before you plan a journey.

Route and stations

The new corridor is 29.6 km of double line suburban railway built by Mumbai Railway Vikas Corporation (MRVC) under MUTP-III, at a sanctioned cost of Rs 2,782 crore according to Ministry of Railways releases published by PIB (PIB release). MRVC’s environmental assessment describes the double line as proposed alongside the existing Panvel to Karjat line (assessment).

Order Station Naming note
1 Panvel Navi Mumbai end
2 Chikhale Intermediate station
3 Poyanje Formerly Mohape. PTI reported on 4 December 2025 that the Ministry of Railways renamed it, with the new code PYJE (PTI report)
4 Chowk Also written Chouk
5 Karjat Karjat end

Schematic route, not to scale: Panvel, then Chikhale, then Poyanje, then Chowk, then Karjat. The corridor includes three tunnels totalling about 3.164 km, including the 2.625 km Wavarle tunnel, with the others reported as Kirawali and Nadhal.

Completion target versus opening date

Item What has been reported Source and date
Construction target MRVC is targeting completion of the work by the end of December 2026, followed by handover to Central Railway Sakal, 7 November 2026
Reported progress About 99% of the project was reported complete at the end of September 2026, with signalling about 95% and passenger facilities at Karjat station, such as the platform, lifts and escalators, in the final stage Sakal, 7 November 2026. A 17 September 2026 report also gave about 99%
Inspection expectation Commissioner of Railway Safety (CRS) inspection described as likely by the end of 2026 HomeBazaar, October 2026, citing MRVC and press reports
CRS clearance No clearance announcement identified in the sources reviewed. Confirm the latest position through official railway updates Not announced
Passenger service start No date announced Not announced

These are separate things. A construction target is when MRVC aims to finish the work. An inspection expectation is when safety inspection is likely. A clearance is an actual approval. A service start is the day trains begin to run, with a timetable. The reports cited do not establish a service start date. A hope for a start around Diwali was reported in September 2026, and no start was announced.

What changes for Navi Mumbai commuters

Panvel is served by Harbour and Trans-Harbour suburban services and also handles mainline trains. The new corridor would add a suburban connection towards Karjat. Our Panvel railway station guide covers the station today, our Panvel area guide covers the area, and our Mumbai local train guide for Navi Mumbai covers the lines that serve Navi Mumbai now.

Reports give no verified timetable, fares, number of trains or travel time for the new service, so none are given here.

Journey options today

For journeys before the new suburban service begins, use the existing travel options described in our Navi Mumbai to Matheran guide and Kondana Caves guide. Check train timings on the National Train Enquiry System or Central Railway’s own channels, and wait for an announcement from Central Railway or MRVC with a date and a timetable before planning around the new line. Treat unsourced social media posts that give an opening date with caution.

How this guide was checked

  • Length and cost come from Ministry of Railways releases published by PIB, which list the Panvel Karjat Suburban Corridor (MUTP-III) at 29.6 km and Rs 2,782 crore.
  • The completion target, handover and progress come from Sakal of 7 November 2026, with the September 2026 figure also in Projects Monitor of 17 September 2026. Both are reports citing MRVC and not an MRVC or Central Railway notice.
  • The CRS inspection expectation comes from HomeBazaar of October 2026 and is labelled as a reported expectation.
  • The Mohope to Poyanje renaming comes from PTI of 4 December 2025.
  • Checked on 15 November 2026.

Frequently Asked Questions

Has the new Panvel to Karjat suburban service started?

No. As of 15 November 2026 no start date for the new suburban local service has been announced. The work was reported at about 99% in September 2026, with MRVC targeting completion by the end of December 2026 and then handover to Central Railway.

Is there already a railway between Panvel and Karjat?

Yes. An existing line connects the two and carries other train traffic. This guide covers the new suburban corridor being built alongside it.

How long is the corridor and what does it cost?

29.6 km, and Rs 2,782 crore sanctioned under MUTP-III according to Ministry of Railways releases published by PIB.

What will the stations be?

Panvel, Chikhale, Poyanje (formerly Mohape), Chowk and Karjat.

Is a December 2026 completion the same as an opening date?

No. It is a construction completion target. Safety clearance from the Commissioner of Railway Safety and a published timetable are needed before passenger service starts.

What is the CRS?

The Commissioner of Railway Safety. A new line needs its inspection and approval before passenger trains can run.

Sources

Point Source
Length, programme and cost PIB, Ministry of Railways
Completion target, handover and progress, 7 November 2026 Sakal
Progress and tunnels, 17 September 2026 Projects Monitor
CRS inspection expectation HomeBazaar, October 2026
Mohope renamed Poyanje PTI, 4 December 2025
Double line alongside the existing line AIIB social impact assessment

Checked 15 November 2026. Targets change, so confirm with Central Railway.

NaviMumbai.com is an independent information site and is not affiliated with any government body.

Pari Chaudhary

Founder & Editor

15+ years in digital, content and creative; a decade living in Navi Mumbai. Writes about the city's neighbourhoods, real estate, transport and daily life.