Atal Setu to Pune Expressway Connector: Route and Status

Transport & Commute

Photo: Amitbalani, Wikimedia Commons, CC0. The Atal Setu (Mumbai Trans Harbour Link) sea bridge with its clock-topped lamp posts and a hazy shoreline in the distance. This is an illustrative photo of the Atal Setu and not of the Chirle to Palaspe connector.

Quick answer: The Chirle to Palaspe connector is a 7.35 km, six lane elevated road that MMRDA is building to link Atal Setu (the MTHL sea bridge) at Chirle with the Mumbai-Pune Expressway at Palaspe. It is not open yet. MMRDA’s April 2026 brief says the project is scheduled for completion by February 2027 (MMRDA brief), and a November 2026 update puts physical progress at 67 per cent (Free Press Journal, 9 November 2026). That is a planned completion target, not an opening date. Until it is ready, drivers heading to Pune use the existing roads.

This is a researched guide and not an official notice. This site is not affiliated with MMRDA, MSRDC or NHAI. Project dates, toll rules and road access change, so confirm with MMRDA before you plan a trip around this road.

Three different projects people mix up

Search results often blur these together. They are separate roads built by different bodies.

Project What it is Status as reported
Atal Setu (MTHL) The sea bridge that MMRDA describes as Atal Setu (Sewri to Nhava Sheva) Already open. See our Atal Setu toll guide.
Chirle to Palaspe connector 7.35 km elevated link between Atal Setu and the Mumbai-Pune Expressway, built by MMRDA Under construction. Target: completion by February 2027 (MMRDA, April 2026)
Pune Missing Link A 13.3 km bypass of the ghat section between Khopoli and Kusgaon near Lonavala, on the Pune side of the expressway Opened on 1 May 2026 (Autocar India; The Hindu, 2 May 2026)

In short, the Missing Link is far from Navi Mumbai, near Lonavala. The connector sits at the Chirle and Palaspe end of the route, next to Navi Mumbai. They do not depend on each other.

Where the connector starts and ends

  • Start: Chirle, where Atal Setu lands in Navi Mumbai. MMRDA says the corridor gives direct, high speed connectivity “via Chirle and Palaspe nodes” (MMRDA brief). Express Belong describes the start as the Chirle interchange where the bridge ends (Express Belong, 9 July 2026).
  • End: Palaspe, where it joins the Mumbai-Pune Expressway near Panvel, according to the same Express Belong page.
  • Build: the Indian Express reported two elevated sections, at Chirle and at Palaspe (Indian Express, 21 April 2026). MMRDA says slip roads and service roads at Palaspe are being widened so traffic can spread out and join the expressway network.
  • Airport: MMRDA says the corridor will also give access to Navi Mumbai International Airport.

The published material does not give the exact ramp positions, merge points or the expressway kilometre marker where the connector joins. Look at MMRDA’s announcements for those when the road nears opening.

Status table: what has been reported

Every row below is a report or a target, and none of it is an opening date.

Item What is reported Source and date
Length and width 7.35 km, six lanes, 11.5 m plus 11.5 m MMRDA brief, 21 April 2026
Foundations Done at 143 of 176 locations MMRDA brief, April 2026
Piers Built at 141 locations, 88 with pier caps MMRDA brief, April 2026
Precast girders 653 of 830 completed MMRDA brief, April 2026
Overall progress 67 per cent physical progress Free Press Journal, 9 November 2026, and Financial Express, 11 November 2026
Planned completion Scheduled for completion by February 2027 MMRDA brief, April 2026; the Financial Express report repeats February 2027 as the slated target
Cost About ₹1,100 crore (reported figure) Express Belong, 9 July 2026
Time saving Between 60 and 90 minutes from South Mumbai to Pune, as reported Free Press Journal, 9 November 2026
Toll for the connector Check MMRDA’s announcements Ask MMRDA

Treat the time saving as a claim for good traffic days. The Financial Express says it depends on traffic conditions. MMRDA says the point of the road is to let motorists reach the Mumbai-Pune Expressway “without any signal interruptions” (MMRDA brief).

What to use today if you are driving from Navi Mumbai to Pune

The connector cannot be used yet, so nothing about your usual trip changes. Here is a practical order of checks.

  1. Take the usual route to the Mumbai-Pune Expressway. Our Navi Mumbai to Pune by road guide covers where it starts, the car toll and the old highway.
  2. If you are coming from South Mumbai over Atal Setu, you still reach the expressway through the Panvel area. The Financial Express reports that the connector is meant to bypass Panvel Main Junction (Financial Express).
  3. Check tolls before you leave. Atal Setu has its own charges, listed in our Atal Setu toll guide. The expressway and other plazas are separate, so see the toll plazas around Navi Mumbai.
  4. If you use a FASTag pass, check where it is valid in our FASTag annual pass guide.
  5. The Missing Link is open, so you may meet it further along the expressway. Check its current rules for your vehicle with MSRDC before you travel, since vehicle restrictions apply to some classes.
  6. Allow for Panvel traffic at peak hours, and check a live map before you set off.

Airport traffic and the connector

MMRDA lists access to Navi Mumbai International Airport as one benefit. If you are heading to the airport, the road is not part of today’s route, so use the options in our how to reach Navi Mumbai Airport. The Navi Mumbai airport vs Mumbai airport explains which airport suits which trip. For another road under development in the same area, see our Thane to Navi Mumbai airport elevated road guide.

Frequently Asked Questions

Is the Chirle to Palaspe connector open?

No. MMRDA’s April 2026 brief describes it as under construction and scheduled for completion by February 2027. That is a planned target, not an opening date.

How long is the connector?

MMRDA says it is 7.35 km long with six lanes, a width of 11.5 m plus 11.5 m.

Where does it start and end?

It runs between Atal Setu at Chirle and the Mumbai-Pune Expressway at Palaspe, near Panvel. MMRDA describes the route as via the Chirle and Palaspe nodes.

Is this the same as the Pune Missing Link?

No. The Missing Link is a 13.3 km bypass between Khopoli and Kusgaon near Lonavala, and it opened on 1 May 2026. The connector is a separate MMRDA project near Panvel.

Will there be a toll on the connector?

Check MMRDA’s announcements for any toll on the connector. Atal Setu itself has tolls, covered in our Atal Setu toll guide.

How much time will it save?

Free Press Journal reported on 9 November 2026 that MMRDA expects a saving of 60 to 90 minutes between South Mumbai and Pune. The Financial Express says it depends on traffic conditions.

What should I use today to reach Pune from Navi Mumbai?

Use the existing route to the Mumbai-Pune Expressway, and check tolls and FASTag before you start. Our Navi Mumbai to Pune road guide has the route and car toll.

How this guide was checked

  • Length, width, structure counts, route nodes, airport access and the February 2027 target come from MMRDA’s project brief dated 21 April 2026.
  • The 67 per cent figure and time saving come from Free Press Journal (9 November 2026) and Financial Express (11 November 2026), both reporting MMRDA updates.
  • The two elevated sections come from the Indian Express (21 April 2026). Cost, start and end description come from Express Belong (9 July 2026).
  • The Missing Link facts come from The Hindu (2 May 2026) and Autocar India (1 May 2026).

Sources

Point Source
Project brief, targets and structure counts MMRDA, April 2026 brief (PDF)
67 per cent progress Free Press Journal, 9 November 2026
Progress, time saving, Panvel junction Financial Express, 11 November 2026
Two elevated sections Indian Express, 21 April 2026
Completion target repeated Moneycontrol, 23 June 2026
Cost and route description Express Belong, 9 July 2026
Missing Link The Hindu, 2 May 2026 and Autocar India, 1 May 2026

Checked 22 November 2026. Targets and road access change, so confirm with MMRDA.

NaviMumbai.com is an independent information site and is not affiliated with any government body.